Hamlet, Richmond County, NC
Amazon Web Services Richmond County data center campus
Also known as Project Blue Marlin, Energy Way
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Amazon Web Services is building a $10 billion data center campus at the county's Energy Way industrial site near Hamlet, next to Duke Energy's Sherwood H. Smith Jr. energy complex. The 646-acre site was sold by Richmond County for $26 million, and county commissioners approved 20-year property tax grants in June 2025. Construction began in fall 2025; local reporting says the first building is expected to open in 2027, with more planned through 2029.
Key facts
Size & schedule
| Site size | 646 acres [3] forest and former chicken farm sold by the county for $26 million |
|---|---|
| Buildings | 21 [3] each 200,000 sq ft, per NC Newsline; DCD reported up to 20 buildings in 2025 |
| Stated investment | $10 billion [1] planned investment |
| Permanent jobs (promised) | 500 [1] at full build-out; county agreement requires $1 billion investment and 50 full-time jobs by 2030 |
| Target completion | First data center projected to open in 2027; more facilities through 2029 [5] |
Power
| Utility | Duke Energy [1] |
|---|
Water
| Water source | Richmond County water system (municipal) [1] Amazon says it will cool with outside air about 93% of the year and pay for water/wastewater extensions |
|---|---|
| Cooling | outside air most of the year, with water-based cooling in peak summer [5] |
Money & incentives
| Tax incentives | County grants of up to 50% of annual real property taxes and 65% of personal property (machinery and equipment) taxes for 20 years [2] |
|---|
Local decisions & site
| Parcel / address | Energy Way Tech Campus, Airport Road, Hamlet [7]Source excerpt“Energy Way Tech Campus data center on Airport Road in Hamlet” |
|---|
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
County drafts confidential purchase agreement with 'Project Blue Marlin' for the site [6]
County commissioners vote to sell county parcels for $26 million and rezone land to heavy industrial [6]
Richmond County commissioners approve property tax incentive grants [2]
Gov. Josh Stein announces the $10 billion Amazon investment [2]
Amazon breaks ground on the campus [4]
NC DEQ holds joint public hearing on the Amazon and Duke Energy air quality permits in Rockingham [8]
State regulators reviewing draft air permits for backup diesel generators after public hearings [6]
NC DEQ announces final air quality permits for Amazon's 588 emergency engines and Duke Energy's 57 bridge power engines [7]
Amazon expected to begin hiring for data center jobs [1]
Issues raised
- Nearby residents say they were not told about the project before county decisions were made [3]
- Air permit applications cover 592 backup diesel generators for Amazon plus 57 for Duke Energy; residents and environmental groups raised emissions and environmental justice concerns [3][6]
- Energy and water terms of the deal were kept confidential [3]
Sources
- AWS Comes to Richmond CountyRichmond County Economic Development · Sep 4, 2026 · government
- Amazon to invest $10 billion into AI data centers in North CarolinaAxios Raleigh · Jun 4, 2025 · news
- Inside the secretive deal for a $10 billion data center in rural North CarolinaNC Newsline · Aug 6, 2026 · news
- Amazon breaks ground on $10bn data center complex in Richmond County, North CarolinaDatacenterDynamics · Oct 31, 2025 · news
- Why one North Carolina county said yes to Amazon's $10 billion data centerWRAL · Jul 20, 2026 · news
- Inside the Secretive Deal for a $10 Billion Data Center in Rural North CarolinaInside Climate News · Aug 4, 2026 · news
- NCDEQ's Division of Air Quality requires additional monitoring, testing in final air quality permits for Amazon data center and Duke Energy projectsNC Department of Environmental Quality · Aug 28, 2026 · government
- DEQ announces joint public hearing on Amazon data center and Duke Energy air quality permits in Richmond CountyNC Department of Environmental Quality · Jun 26, 2026 · government