Panattoni Development is linked to 2 tracked projects in Ohio, Michigan, totaling 1.24 GW of planned capacity. Role: developer.

ProjectStatusCapacityDeveloperLast update
Perry Township Data Center
Canton, Stark County, OH
Approved 240 MW Panattoni Development Jun 2026
Project Cannoli
Van Buren Township, Wayne County, MI
Approved 1 GW Panattoni Development Aug 3, 2026

Recent changes

  1. Project Cannoli MI
    Michigan Attorney General files brief opposing DTE's proposed 80% minimum billing demand Planet Detroit
  2. Perry Township Data Center OH
    Stark County Board of Commissioners approves the project 2-0 WHBC
  3. Project Cannoli MI
    Board of Trustees meeting on the project; development agreement dated May 20 Charter Township of Van Buren
  4. Project Cannoli MI
    Planning Commission approves site plan for substation/switching station Planet Detroit
  5. Perry Township Data Center OH
    Panattoni hosts an open house at Perry High School on the project Ideastream Public Media
  6. Project Cannoli MI
    Google and DTE Energy confirm Google as the company behind the project; Google commits to a contested case at the MPSC Michigan Advance
  7. Project Cannoli MI
    Planning Commission grants preliminary site plan approval 5-2 Planet Detroit
  8. Perry Township Data Center OH
    Perry Township trustees and the city of Canton approve the project under a JEDD agreement WHBC

This page lists projects in the Census where Panattoni Development is named as developer by a cited source. It is not a complete list of the company’s facilities.