Taylor, Williamson County, TX
Blueprint Taylor Data Center
Also known as Blueprint Projects Data Center, Blueprint Taylor DC
- Rumored
- Proposed
- Approved
- Under construction
- Operating
Blueprint is planning a 135,000-square-foot, three-building data center on a 52-acre parcel in southeast Taylor. The land had been conveyed in 1999 to be held in trust as future parkland; the Taylor Economic Development Corporation sold it to the developer for $10,000,000 on April 11, 2025. The City Council approved the project's Employment Center Plan unanimously on July 24, 2025. Residents are appealing a lawsuit over the land, and Texas Attorney General Ken Paxton has launched an investigation into the deal.
Key facts
Size & schedule
| Planned capacity | 60 MW [2] ultimate target; initial power agreement with Oncor for 30MW Source excerpt“has a power agreement with Oncor for 30MW of power. Ultimately, the data center hopes to reach 60MW” |
|---|---|
| Site size | 52 acres [2]Source excerpt“The data center will be located on a 52-acre parcel at 1601 Martin Luther King Jr. Drive in Taylor” |
| Floor area | 135,000 sq ft [1]Source excerpt“135,000 square foot data center” |
| Buildings | 3 [1]Source excerpt“three buildings, an electricity substation to power it, backup power generators, and a closed-loop cooling system” |
| Stated investment | $1 billion [1] three phases Source excerpt“three phases with a total investment of $1 billion” |
| Permanent jobs (promised) | 20-30 [2] range: between 20 and 30 jobs Source excerpt“for the data center to create between 20 and 30 jobs” |
| Target completion | Energized by 2027 [3]Source excerpt“The project planned for Taylor is expected to have a capacity of 60 megawatts and will be energized by 2027.” |
Power
| Utility | Oncor [2] power agreement for 30MW Source excerpt“has a power agreement with Oncor for 30MW of power” |
|---|---|
| Power supply | Electric grid, via an on-site electricity substation [1]Source excerpt“The project will be connected to the electric grid for power supply.” |
| Backup generators | backup power generators [1]Source excerpt“three buildings, an electricity substation to power it, backup power generators, and a closed-loop cooling system” |
Water
| Cooling | closed-loop [1]Source excerpt“three buildings, an electricity substation to power it, backup power generators, and a closed-loop cooling system” |
|---|
Money & incentives
| Tax incentives | Chapter 380 Economic Development Agreement with BPP Projects LLC, authorized by City Council August 8, 2024 [1]Source excerpt“Taylor City Council authorized a Chapter 380 Economic Development Agreement with BPP Projects LLC | August 8, 2024” |
|---|
Local decisions & site
| Deciding vote | Taylor City Council approved the Employment Center Plan unanimously on July 24, 2025 [2]Source excerpt“received unanimous approval from the council on July 24” |
|---|---|
| Zoning | Designated Employment Center on the future land use map [1]Source excerpt“the property in question was designated employment center in the future land use map” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Bonnibel Bland Cromwell and relatives convey the roughly 87-acre tract to the Texas Parks and Recreation Foundation [3]
Taylor EDC approves agreement with BPP Projects LLC [1]
City Council authorizes a Chapter 380 Economic Development Agreement with BPP Projects LLC [1]
Taylor EDC sells the property to the developer for $10,000,000 [1]
Planning & Zoning Commission holds public hearing on the Employment Center Plan [1]
City Council approves the Employment Center Plan [1]
Appeal by residents against NCP Travis TPP Project, LLC is pending before the Fifteenth Court of Appeals [6]
Texas Attorney General Ken Paxton launches an investigation into the land deal [3]
Issues raised
- Residents raised concerns about noise, light pollution, electromagnetic fields, water and air pollution [4]
- The Halt Taylor Data Center Coalition delivered a petition of 14,000 signatures to the City Council [4]
- Residents say the land was given to be held in trust for parkland; the Attorney General says he will seek court intervention if the property is subject to a charitable trust [3][5]
Sources
- Blueprint Projects Data CenterCity of Taylor, TX · government
- Blueprint Projects gets greenlight for data center in Taylor, TexasDatacenterDynamics · Jul 28, 2025 · news
- Paxton Begins Investigation into Data Center Land DealTexas Scorecard · Sep 17, 2026 · news
- Proposed data center in Taylor draws pushback from communityFOX 7 Austin · Jun 11, 2026 · news
- Texas Family Donated Land for a Park—Now a Data Center Is Being Built on ItNewsweek · Jun 20, 2026 · news
- Pamela Griffin, et al. v. NCP Travis TPP Project, LLC (appellee's motion for extension, No. 15-25-00202-CV)CourtListener · Dec 19, 2025 · court