College Station, Brazos County, TX
Project Aggie
Also known as College Station Midtown data center
DeniedCity Council unanimously rejected sale of city land on 2025-09-11
- Rumored
- Proposed
- Approved
- Under construction
- Operating
- Denied
Priority Power Management sought to buy about 200 acres of city-owned land in College Station's Midtown Business Park for a data center campus the developer said would serve AI, planned at up to 600 MW. The College Station City Council unanimously rejected the $30 million land sale on September 11, 2025, after hours of public comment from opponents.
Key facts
Size & schedule
| Planned capacity | 600 MW [3] at full build-out |
|---|---|
| Site size | 200 acres [2] approximately |
| Stated investment | $30 million [4] land purchase price ($150,000/acre); $1-4 billion capital expenditure cited for full development |
Local decisions & site
| Deciding vote | College Station City Council unanimously voted to deny the real estate contract with Priority Power Management after a public hearing on September 11, 2025 [6]Source excerpt“After a public hearing, the Council unanimously voted to deny a real estate contract with Priority Power Management for the sale of about 200 acres of City-owned property in the Midtown Business Park near Midtown Drive and Corporate Parkway.” |
|---|---|
| Parcel / address | About 200 acres of City-owned property in the Midtown Business Park near Midtown Drive and Corporate Parkway [6]Source excerpt“the sale of about 200 acres of City-owned property in the Midtown Business Park near Midtown Drive and Corporate Parkway” |
| Nearest homes or schools | 600-900-foot green belt to be retained between the proposed development and nearby homes [7] as described by the city Source excerpt“The city argues the noise pollution will be addressed in part by their retention of a 600-900-foot green belt between the proposed development and nearby homes.” |
Figures are as stated by the cited source. Where sources disagree, each figure is shown.
Timeline
Issues raised
- Residents cited noise, infrastructure strain, and property values; a petition against the sale drew more than 5,000 signatures [2][3]
- Some residents and press described the project as crypto mining; the company's CEO said it would be for AI, not crypto or bitcoin mining [1][5]
- City staff projected $10-22 million a year in revenue to the city [4]
Sources
- College Station City Council Unanimously Votes Against The Sale Of City Land For A Data CenterWTAW · Sep 12, 2025 · news
- College Station City Council unanimously rejects land sale for AI data centerKBTX · Sep 12, 2025 · news
- College Station, Texas rejects land sale for data centerData Center Dynamics · Sep 15, 2025 · news
- College Station considers $30M land deal for data centerKXXV · Sep 8, 2025 · news
- Residents versus revenue: College Station's high-stakes vote on crypto data mining center loomsKXXV · Sep 10, 2025 · news
- Live from City Hall: Thursday's City Council meeting (Sept. 11)City of College Station · Sep 11, 2025 · government
- College Station City Council to discuss potential data center on Midtown Drive at Sept. 11 meetingKBTX · Sep 7, 2025 · news